HomeMy WebLinkAboutADP 2013-09-10 minutes.pdfAdvisory Design Panel Minutes Page 1 of 3
District of Maple Ridge
MAPLE RIDGE
ADVISORY DESIGN PANEL
The Minutes of the Regular Meeting of the Maple Ridge Advisory Design Panel held in the
Blaney Room at Maple Ridge Municipal Hall,11995 Haney Place,Maple Ridge,British
Columbia, on Tuesday, September 10, 2013 at 4:00 pm.
COMMITTEE MEMBERS PRESENT
Blair Arbuthnot Landscape Architect
Chris Mramor, Vice-Chair Landscape Architect
Johnny Leung Architect
Peter Lovick, Chair Architect
Colleen Dixon Architect
COMMITTEE MEMBERS ABSENT
STAFF MEMBERS PRESENT
Rasika Acharya Planner II & ADP Staff Liaison
Joanne Georgelin Committee Clerk
______________________________________________________________________
________
1.Call to Order and Introduction s
The meeting was called to order at 4:16 pm.
2.Agenda Approval
Moved and Seconded :
Th at the September 10 , 2013 agenda be approve d with the following change:
Removal of item 5.2
CARRIED
3.Approval of the Minutes – August 13 , 2013
Moved and Seconded :
That the Minutes of the meeting of August 13 , 201 3 be approved.
CARRIED
4.New Business
Tandem Parking – Rasika Acharya
Maple Ridge Advisory Design Panel
Tuesday, September 10, 2013 - Draft
Maple Ridge Advisory Design Panel Minutes Page 2 of 3
Rasika Acharya welcomes any further feedback or comments,emailed to her,
from the Panel regarding Tandem Parking.
Panel members agreed that 1005 tandem parking townhouse developments
seem to be exist predominantly in city centre or town centre area that supports
dense developments and that it is good idea to balance Tandem and double
garage developments in all the other areas,to keep it a low density multi-family
option.Colleen Dixon pointed out that tandem parking does make the unit more
affordable and more efficient to park two vehicles,but is usually the last choice
when there are site constraints.Ms.Dixon confirmed that buyers generally prefer
double garage townhouses to tandem.
5.Projects
5.1 Development Permit:2012-021-DP (revised proposal by new
architect)
Applicant:David Laird, Damax Consultants
Project Architect: Mark Lesack, MAIBC, Ankenman
Associates Architects Inc.
Landscape Architect: Meredith Mitchell
Proposal: Proposed mixed use building totaling 702.6
m2 (7,563.5 ft2) and two apartments on the
proposed C 1 zoned lot
Location: 11185 240 Street
Planner/ File Manager: Adrian Kopystynski
The following applicants were present at the meeting:
Emily Kearns, Architect
Mark Lesack, Architect
Rasika Acharya reviewed the Advisory Design Panel Memo dated September 10,
2013 attached to the agenda,with respect to the location,context,surrounding
buildings,OCP designation and Commercial DP Guidelines,site access,site
size,proposed design and density,form,phases (remove),off-site upgrades,
rezoning application,building materials,sanitary sewer connections,landscaping
and parking.Ms.Acharya added that this permit had come to the panel
previously,but with a new owner it went through design changes and was
required to be re-submitted to the Advisory Design Panel.
Emily Kearns,Intern Architect,presented the proposed design details.The
Landscape Architect,Meredith Mitchell was absent and had provided notes for
the project architect to convey to the Panel.
Mark Lesack,Architect,explained to the Panel why this application has changed
from a four residential unit to a two residential unit and clarified a few details and
answered questions.
Maple Ridge Advisory Design Panel
Tuesday, September 10, 2013 - Draft
Maple Ridge Advisory Design Panel Minutes Page 3 of 3
Moved and Seconded :
The following concerns be addressed and digital versions of revised drawings
&memo be submitted to Planning staff;and further that Planning staff forward
this on to the Advisory Design Panel for information.
Consider using the roof brackets at the corner of roof feature
Provide a pathway access to PMT
Provide backup space at north end of the parking area
Consider adding gables on the roof line
Consider carrying the brick columns around the main corner feature
Consider grouping residential entries together (stairs)
Provide details for architectural concrete treatment
Show the location of the electrical room
Consider planters or details of architectural treatments along the sidewalk
at the south-east driveway
Consider sign band along rear of commercial building
Provide details of the roof brackets
Consider concrete pedestals for brick columns
Provide detail s for grades along hard landscape areas
Clarify the sidewalk/landscape treatment along the east wall
Consider using pavers between propert y line and building (north and east)
Consider wheel -stop provision along the west bank of parking to match
others proposed
Look at si ght lines along the fence line for vehicle entry from the lane
Consider deletion of one of the brick pilasters where they are grouped
together
Consider more accessible bike parking areas.
CARRIED
6.PRESENTATIONS - Nil
7.CORRESPONDENCE - Nil
8.Next Meeting :Tuesday , October 8 , 2013
Agenda deadline:Monday, September 16, 2013
Adjournment:5:19 pm